Project Schedule
The regulations and standards established by this local law shall be automatically canceled and the lands comprising the Lake Flower Planned Unit Development District shall revert to their prior zoning districts (B1 or B2) if the following milestones are not achieved:
 
Table 15.1 - Project Schedule
Milestone Deadline
Site Plan Approval Within one year from the date of adoption of this local law.
Project Start (Issuance of a Building Permit) Within one year from the date of site plan approval by Planning Board
Project Completion (Issuance of a Certificate of Occupancy or Temporary Certificate of Occupancy) Within twenty four (24) months following the date of issuance of a building permit

1. The applicant may seek up to two (2) extensions to a deadline by submitting a written request to the Village Board at least 60 days prior to the deadline. The request shall set out the reasons for the extension request.

2. Milestone deadlines shall be suspended upon the issuance of a court-ordered injunction and/or cease & desist order and shall resume at such time the injunction and/or order is removed.

3. Grant of extension of any deadline shall not require an amendment to this local law and the applicant shall not be required to submit a new or amended PUDD application.

See Attachment 4 for complete, detailed information about the Lake Flower Planned Unit Development District.